Services / Mark III membrane systems

How we work · 8 steps

Mark III layer by layer

The membrane system of an LNG tank (−163 °C) — from hull marking to the corrugated membrane and tightness tests. Scroll: the tank wall assembles step by step, and for each step you see what we do, why, and what we check.

LNG carriersFSRU / FSUTanks on GBSOnshore tanks70+ specialists with Mark III experience

Membrane tank wall · schematic

Schematic of the Mark III membrane systemOn the left is a section of the cargo tank, on the right a fragment of its wall. As you scroll, layers appear in turn: the hull with marking and embedded fittings, mastic ropes, insulation panels, the secondary barrier, the top insulation layer, and a corrugated stainless-steel membrane; then tightness tests and acceptance. LNG −163 °C CARGO TANK · SECTION TANK WALL —DETAIL He
01/ 08 Marking

Schematic diagram

Marking and embedded fittings

We accept the inner hull of the tank, carry out the marking and install the anchors and embedded fittings that the whole system rests on.

WhyThe membrane system is fixed directly to the hull: the position of every panel and every membrane weld depends on the accuracy of the marking.

ChecksCondition and cleanliness of the hull surface, accuracy of the marking, and the position of embedded fittings — as designed.

Resin ropes (mastic)

We apply resin ropes (mastic) in rows along the marking — the insulation panels sit on them.

WhyThe hull is never perfectly flat: the ropes take up irregularities and transfer the load from the panels to the hull evenly.

ChecksPosition and spacing of the ropes, pot life of the mastic, and temperature and humidity in the tank.

R-PUF insulation panels

We install and level panels of reinforced polyurethane foam (R-PUF) with plywood facing.

WhyThe panels are the main thermal insulation layer: they keep the −163 °C cold inside and transfer the cargo pressure to the hull.

ChecksLevelling the panels into a common plane, the gaps between panels, and fixing to the embedded fittings.

Triplex secondary barrier

We fill the joints and bond the Triplex secondary barrier — a composite of aluminium foil and glass cloth — overlapping the panel joints.

WhyThe secondary barrier is the second line of tightness: if the membrane is damaged, it holds the LNG and protects the hull from the cold.

ChecksSurface preparation for bonding, application without bubbles or wrinkles, and a tightness test of the secondary barrier.

Top insulation layer

We close the joints of the top layer with insulation inserts and level the surface for the membrane.

WhyThe membrane needs a continuous, even base: there must be no steps or voids left underneath it.

ChecksContinuity of the insulation at the joints and flatness of the base for the membrane.

Primary 304L membrane

We install corrugated 304L stainless-steel sheets 1.2 mm thick and weld them: automatic and semi-automatic TIG welding, with manual welding at nodes and corners.

WhyThe membrane is in direct contact with the LNG. The corrugations act as compensators: as the metal cools and contracts, the corrugations take up the deformation.

ChecksAppearance and continuity of the welds, and alignment of the corrugations at the sheet joints.

Tightness tests

We check the tightness of the membrane and the welds with a vacuum box and with ammonia and helium tests.

WhyOnce the tank is closed and cooled down, finding and fixing a leak is far harder. Every remark is corrected and checked again.

ChecksMethods and criteria follow the project test programme; results are recorded in the reports.

As-built documentation

We hand over the works and pass on the as-built documentation for each stage.

WhyThe layers under the membrane are no longer visible — the documents confirm that each one was completed and checked.

Checks and documents

  • Work logs
  • Test reports
  • As-built drawings
Contacts

Let’s discuss your project

Send a design or a scope of work — we will prepare a proposal for Mark III membrane works.

info@mesa-eng.com

The diagram is schematic: it shows a typical work sequence, without scale or dimensions. The construction, materials and test methods are set by the design.